The travel path, clearances and the fall zone

1 min read

The route from pick point to set point is planned on the ground, before anything is attached. The rigger walks the whole path looking for overhead and side clearances, obstructions and pinch points.

Each restriction is checked against the load's dimensions plus the height the rigging adds above it, and if the load will not pass with room to spare, the route or the rigging changes.

Example: a crate 7 ft tall hung on rigging that adds 6 ft above it needs more than 13 ft of clear height under a mezzanine, plus a margin, before the hook height is even considered. Letting the signal person judge each gap by eye as the load arrives is not planning.

The fall zone is the area a load or part of it could fall into, and workers not engaged in the lift are kept out of it, under OSHA's crane rules in 1926.1425. Any place where a moving load closes on a fixed column or wall is a pinch point, and no one stands in that gap.

Power lines are treated as energized until the utility owner or operator confirms they are de-energized and visibly grounded at the worksite; a site worker's word is not confirmation. Areas that must be cleared are barricaded before the load moves.

Check yourself

1. The planned path for a suspended load passes under a mezzanine, alongside racked material and through a doorway. How should the rigger treat those restrictions?

2. During the pre-lift assessment, a rigger plans how a load will travel from the lay-down yard to its setting location. What does identifying the travel path require?