Chapters0/29 ▾
Chapter 2 · Lesson 2 of 4
Prevention versus detection: cost of quality and inspection points
1 min read
The cost-of-quality model sorts quality spending into four buckets. Prevention, such as training, capable process design and error-proofing, stops defects from being made and costs the least. Appraisal is inspection and testing. Internal failure is scrap, rework and re-test inside the plant.
External failure, such as returns and warranty claims, costs the most because the defect reached the customer. Final inspection alone cannot build quality in, because by the time a part is checked the material, machine time and labor are already spent.
- First-article inspection checks the first piece after a setup, before the run continues, so a bad setup costs one part instead of a whole lot.
- In-process inspection catches drift or tool wear while the job runs, limiting scrap to the parts made since the last check; it adds to final inspection rather than replacing it.
- Sampling judges a lot from part of it, so a lot with defects can be accepted or a good lot rejected, and even 100 percent inspection misses defects through fatigue and error.
Example: a team adds a fixture pin so a bracket can only be loaded one way. That spending is prevention, and it is the cheapest bucket because it stops the wrong-way part from ever being made.
Check yourself
1. In the cost of quality, which category normally costs a manufacturer the least?
2. Why does relying on final inspection alone fail to build quality into a product?
Facts checked 2026-11-15 · Sources: MSSC: Certified Production Technician (CPT 4.0), NIST/SEMATECH e-Handbook of Statistical Methods: Introduction to control charts