PM discipline, maintenance records and warning signs
1 min read
A preventive maintenance task is scheduled before failure on purpose, so the exam rewards protecting it. If a PM comes due while the line is behind, the technician tells the supervisor and planner so it is formally rescheduled and the deferral is documented.
Skipping it, doing only part of it, or signing the checklist now and working later all trade a short planned stop for a long breakdown and corrupt the record.
- A PM is complete when it is entered in the maintenance record, not when the last grease point is done or the machine restarts.
- Repair history turns single events into patterns. The same repair three times points to a root cause such as misalignment, contamination or overloading.
Operators also use their senses. Heat, a new noise and a burnt smell showing up together are classic signs of an advancing failure, such as a gearbox whose lubricant film has broken down.
The operator-level answer is to stop the machine, tag it out of service and submit a work request. Running to the end of the shift, topping off the oil, or cooling it with a fan all leave the damage growing.
Example: a technician finishes greasing a conveyor but is called away before logging it. Until the entry is made, the plant cannot prove the work was done or set the next due date from it.
Check yourself
1. An operator notices a gearbox running hot, with a new whine and a burnt-oil smell. What is the correct action?
2. A preventive maintenance task on a press comes due, but the line is behind schedule. What should the technician do?