Chapters0/29 ▾
Chapter 4 · Lesson 4 of 5
Volume, setup cost, takt time and the bottleneck
1 min read
Tooling such as a stamping die or an injection mold is a fixed cost paid once, so cost per piece falls as quantity rises.
Example: a $12,000 die spread over 100 parts adds $120 to each one, but spread over 100,000 parts it adds only $0.12. A prototype, a handful of parts, or a design that still changes every week points to flexible machining instead.
Changeover works the same way. While a machine is being changed it makes nothing, and that lost time is carried by the parts in the next run.
Example: a 60-minute setup spread over 30 parts costs 2 minutes of machine time per part, but over 300 parts only 0.2 minute. Quick-changeover work moves setup steps off-line so the machine stops for less time.
Takt time is the pace customer demand sets: available production time divided by units needed. Example: 450 available minutes and a demand of 150 units gives 3 minutes per unit. Dividing the other way, 150 by 450, gives a rate in units per minute, not a takt time.
Separately, on a line that runs in sequence, the slowest station is the bottleneck. With stations of 25, 50 and 35 seconds, the line can finish at best one unit every 50 seconds, or 72 per hour.
Check yourself
1. A cell has 420 minutes of available production time in a shift, and the customer needs 210 units per shift. What is the takt time?
2. A planner is deciding between machining a bracket one at a time and building a stamping die for it. Which condition most favors building the die?
Facts checked 2026-11-15 · Sources: MSSC: Certified Production Technician (CPT 4.0)
Production Technician cheat sheet: every key fact on one page →