Make-ready turns, inspections and curb appeal
1 min read
A turn is sequenced to avoid rework. Repairs come first because patching, sanding and installing parts leave dust and marks that paint will cover. Paint comes next, then cleaning removes drips and dust, and carpet cleaning goes last so no other trade tracks dirt onto damp, freshly cleaned carpet.
If the painter is ready before the drywall patches are sanded or the new countertop is set, the painter waits, because those jobs leave surfaces that need paint.
- Re-key the locks during the turn so no one outside the office holds a working key when the new resident moves in.
- Test every smoke and CO alarm and replace any that fail, which also creates a dated record that they worked at move-in.
- At the final walk, write each deficiency on a punch list, assign it, and re-inspect until every item is closed.
Curb appeal is every employee's job all day, not one department's task during tours. The building exterior checklist is a planning document: it records conditions so repairs can be scheduled, re-checked after the work and budgeted.
Check yourself
1. A vacant home is being made ready for a new resident. Which order of trades best avoids rework?
2. During a turn, the painter can start tomorrow, but the drywall patches still need sanding and a new countertop has not been installed. Why should painting wait?