Quibank app: now on the App Store — free, works offline. Get the app ↗

Chapters0/24 ▾
← Site Assessment & Setup

Chapter 3 · Lesson 1 of 4

Ground conditions and ground bearing pressure

1 min read

OSHA 1926.1402 defines ground conditions as the ability of the ground to support the equipment, including slope, compaction and firmness.

The crane may not be assembled or used unless the ground is firm, drained and graded so that, together with supporting materials such as mats and blocking, the manufacturer's requirements for support and level are met. Mats spread the load; they cannot create bearing capacity the soil does not have, and keeping lifts light does not cure a soil failure.

  • The controlling entity, the one with overall responsibility for the site, makes sure ground preparation is provided and tells the user and operator about known hazards below the setup area, such as voids, tanks and utilities.
  • If the assembly/disassembly director or the operator finds the ground inadequate, work stops and that person's employer discusses the needed preparation with the controlling entity.
  • Fresh, uncompacted backfill over a trench is not used until a qualified person evaluates it; watching the floats for settling proves nothing.

Ground bearing pressure is the imposed load divided by the contact area. Example: an outrigger corner carrying 32,000 lb on a 4 ft by 4 ft mat (16 sq ft) imposes 32,000 / 16 = 2,000 psf; on a bare 2 ft by 2 ft float (4 sq ft) it would be 8,000 psf.

Whether 2,000 psf is acceptable is decided by a qualified person who knows the soil. Remember that swinging the boom moves the load toward one corner, which can carry far more than a quarter of the total, so mats are sized for the worst boom position.

Check yourself

1. Two days of heavy rain have left the planned crane set-up area soft, rutted, and holding standing water. Before the crane may be assembled or used at that location, what condition must exist?

2. The only position that gives the crane the radius it needs sits directly over a utility trench that was backfilled last week and has not been compacted or tested. What is the correct response?

Facts checked 2026-11-15 · Sources: OSHA 29 CFR 1926.1402: Ground conditions, OSHA 29 CFR 1926.1408: Power line safety (up to 350 kV), equipment operations, OSHA 29 CFR 1926.1404: Assembly/Disassembly, general requirements

Crane Operator (NCCCO) cheat sheet: every key fact on one page →