1 min read

Load chart values are static ratings with no allowance for acceleration. Snatching a stuck load, taking up slack rope suddenly or stopping a descending load quickly adds dynamic force on top of the static weight, so a crane lifting less than its chart rating can still be overloaded. Smooth control and reduced speeds are requirements, not style.

  • A fast swing throws the load outward like a pendulum, lengthening the radius and cutting capacity, and adds side force to the boom.
  • Dragging a load sideways is prohibited at any weight, because booms are designed to carry load in their vertical plane and side load can buckle them.
  • The boom deflects as the load comes on, so the loaded radius is longer than the radius measured with the hook empty.

If the crane goes light and the overload alarm sounds mid-swing, stop, then reduce the load moment: shorten the radius or lower the load straight down at the shortest safe radius.

Swinging quickly to open ground or booming out to reach the landing makes it worse. Example: a load swung too fast drifts from a 40 ft radius to 43 ft; on a chart where capacity falls with every foot, that drift alone can carry a near-capacity lift past the limit.

Check yourself

1. What happens to a suspended load when the operator swings too fast and then stops the swing abruptly?

2. Why can starting or stopping a load abruptly overload a crane that is lifting less than its chart capacity?

Facts checked 2026-11-15 · Sources: OSHA 29 CFR 1926.1416: Operational aids, OSHA 29 CFR 1926.1431: Hoisting personnel, OSHA 29 CFR 1926.1417: Operation