Inspections & Safety Requirements Study Guide — Crane Operator (NCCCO)
30 free practice questions
This part of the exam is mostly about the federal construction crane standard, OSHA 29 CFR 1926 Subpart CC: who inspects the crane and how often, when wire rope must come off, which devices stop the job when they fail, and who has authority on site. The questions reward exact recall of the tiers and numbers, so this chapter lays them out side by side. Your employer's policy can be stricter than these rules, never looser.
Key takeaways
- Shift and monthly inspections are done by a competent person, the annual by a qualified person, and only the monthly (3 months) and annual (12 months) must be documented.
- Running rope comes off at 6 random broken wires in one lay or 3 in one strand in one lay, or when diameter drops more than 5 percent below nominal.
- A rope that has contacted an energized power line is replaced and may not be repaired.
- Safety devices such as boom stops and the level indicator have no repair window: if one is not working, operations do not begin.
- Certification is not authorization; the employer must still evaluate the operator on the specific machine.
Lessons in this chapter
4 short lessons · 4 min read
- 1Crane inspections: who, when and what gets written down1 min
- 2Wire rope removal from service1 min
- 3Safety devices, tagged equipment and cab documents1 min
- 4Stop authority, swing areas and operator authorization1 min
Facts checked 2026-11-15 · Sources: OSHA 29 CFR 1926.1412: Inspections, OSHA 29 CFR 1926.1413: Wire rope, inspection, OSHA 29 CFR 1926.1415: Safety devices
Crane Operator (NCCCO) cheat sheet: every key fact on one page →Practice questions based on the published NCCCO mobile crane operator exam outlines and the consensus safety practices the trade runs on. CCO and NCCCO are marks of the National Commission for the Certification of Crane Operators; this site is not affiliated with or endorsed by NCCCO. Capacity always comes from the load chart for the machine and configuration in front of you, and wind, ground-bearing and permit limits are set by the manufacturer's manual and the authority having jurisdiction — never from a practice question. Confirm current exam requirements before testing. About CCO certification →