Crane inspections: who, when and what gets written down

1 min read

OSHA 1926.1412 sets up regular inspections and event-triggered inspections. The exam usually changes one detail in an otherwise correct answer, such as the person, the interval or the retention period, so learn the three together.

InspectionDone byRecord required by the rule
Each shiftCompetent personNone
MonthlyCompetent personKept at least 3 months
Annual/comprehensiveQualified personKept at least 12 months
  • After assembly, a qualified person confirms the crane is configured to manufacturer criteria before use.
  • Equipment idle for 3 months or more gets a monthly-level inspection by a qualified person before initial use.
  • Severe service, such as shock loading or exceeding rated capacity, stops use until a qualified person checks for structural damage.
  • Level is checked before each shift and again after each move and setup.

When an inspection finds any deficiency, such as a hydraulic hose weeping at a fitting, the competent person decides right away whether it is a safety hazard. If it is, the crane is out of service until it is corrected. Many employers require a written shift checklist; that is good policy, but it is company policy, not the regulation.

Check yourself

1. Under the OSHA construction crane standard, who must perform the monthly inspection of a mobile crane, and how long must the record be kept?

2. During a shift inspection a competent person finds a hydraulic hose weeping oil at a fitting. What does the OSHA construction crane standard require next?