OSHA 1926.1412 sets up regular inspections and event-triggered inspections. The exam usually changes one detail in an otherwise correct answer, such as the person, the interval or the retention period, so learn the three together.
| Inspection | Done by | Record required by the rule |
|---|---|---|
| Each shift | Competent person | None |
| Monthly | Competent person | Kept at least 3 months |
| Annual/comprehensive | Qualified person | Kept at least 12 months |
- After assembly, a qualified person confirms the crane is configured to manufacturer criteria before use.
- Equipment idle for 3 months or more gets a monthly-level inspection by a qualified person before initial use.
- Severe service, such as shock loading or exceeding rated capacity, stops use until a qualified person checks for structural damage.
- Level is checked before each shift and again after each move and setup.
When an inspection finds any deficiency, such as a hydraulic hose weeping at a fitting, the competent person decides right away whether it is a safety hazard. If it is, the crane is out of service until it is corrected. Many employers require a written shift checklist; that is good policy, but it is company policy, not the regulation.
Check yourself
1. Under the OSHA construction crane standard, who must perform the monthly inspection of a mobile crane, and how long must the record be kept?
2. During a shift inspection a competent person finds a hydraulic hose weeping oil at a fitting. What does the OSHA construction crane standard require next?
Facts checked 2026-11-15 · Sources: OSHA 29 CFR 1926.1412: Inspections, OSHA 29 CFR 1926.1413: Wire rope, inspection, OSHA 29 CFR 1926.1415: Safety devices