Chapters0/29 ▾
Chapter 1 · Lesson 3 of 5
Load path, columns and floor framing
1 min read
Every load in a house has to travel without a break from roof to rafters or trusses, to walls and headers, to joists, to girders and columns, to foundation walls and footings, and finally to the soil.
The exam tests this by describing a missing link: a remodel post that lands on the floor over ordinary joists with nothing beneath it, or a girder supported by a post that is not fastened top or bottom and sits on the slab instead of a footing. A slab is not a footing.
Notches and holes are judged by bending stress, not by memorized fractions. At mid-span the bottom fibers of a joist are in maximum tension and the top fibers in compression, while wood near mid-depth carries little stress.
A notch in the bottom edge at mid-span removes the most stressed wood and adds a sharp corner where cracks start, so it is far worse than a round hole bored near the middle of the depth.
A springy floor with no visible damage is still reportable as a stiffness and serviceability concern. The right report describes the bounce, recommends evaluation, and notes that a visual inspection does not determine whether framing sizes and spans are adequate. Calling the joists undersized or specifying sistering is engineering, not inspection.
Check yourself
1. Two identical floor joists of the same span have each had material removed at mid-span: one has a notch cut into its bottom edge, the other has a round hole bored near mid-depth. Why is the notch the greater structural concern?
2. A floor feels noticeably springy underfoot, but the visible joists and girder show no sagging, cracking, decay, or loss of bearing. What is the best way for the inspector to handle this?
Facts checked 2026-11-15 · Sources: National Home Inspector Examination (EBPHI), InterNACHI Home Inspection Standards of Practice
Home Inspector Practice Test (NHIE) cheat sheet: every key fact on one page →