Current has to pass through every part of the service in series: service conductors, meter enclosure, main disconnect and panel bus. The weakest link therefore sets the usable capacity, whatever the other labels say. Example: the panel label reads 200 amps, the meter base is marked 200 amps and the main breaker handle reads 150 amps.
The service is reported as 150 amps. When labels conflict or no rating can be read, the inspector reports the rating as undetermined and recommends an electrician. Performing a load calculation is outside a visual inspection.
Overhead conductors are judged by the principle behind clearance rules: nobody should be able to touch them from a deck, window, stair or walking surface.
A drop within reach is reported as a safety hazard whether or not it looks insulated, because weathered utility covering cannot be trusted. The inspector reports the condition rather than measuring it against a code number.
A drip loop below the weatherhead gives water a low point to drip off. Without it, the entry becomes the low point and water follows the conductors into the meter enclosure and panel, which is why rust staining inside the meter base goes with a missing loop.
Check yourself
1. At a dwelling, the panelboard label indicates one ampere rating, the main disconnect handle is marked with a lower rating, and the meter enclosure carries yet another marking. How should the inspector determine and report the service capacity?
2. Overhead service conductors cross the rear yard and pass beside a second-floor deck, close enough that a person standing on the deck could touch them. What is the inspector's most appropriate response?