Quibank app: now on the App Store — free, works offline. Get the app ↗

28 Operations & Operational Aids Practice Questions & Answers

Every Operations & Operational Aids practice question from the Crane Operator (NCCCO) Practice Test, with the correct answer and a short explanation.

Start practice test →
  1. 1. A mobile crane is equipped with a load moment indicator (LMI). Which statement correctly describes how the operator should use it?

    • A.The LMI measures the ground bearing pressure under the outriggers and confirms the setup is adequate.
    • B.The LMI replaces the load chart once the crane's configuration has been entered into it.
    • C.The LMI is an operator aid: the operator must still verify the load weight and the radius and work within the load chart.✓ Answer
    • D.The LMI allows the operator to keep lifting until the alarm sounds, because the alarm marks the crane's true limit.

    An LMI compares the load being lifted with the rated capacity for the configuration the operator has entered, so its output is only as good as that entry, its calibration and its sensors. Federal rules classify it as an operational aid, which by definition supplements — never replaces — the operator's own verification of weight and radius and the manufacturer's load chart, and rated capacity must never be reached by deliberately 'running into' the alarm.

    Ref QB-S2246VSource: OSHA 29 CFR 1926.1416, Operational aids; ASME B30.5, Mobile and Locomotive CranesReport a problem with this question

  2. 2. During a shift the crane's load moment indicator stops working. Under the federal operational-aid rule, what is permitted?

    • A.Work may continue as long as every lift is kept below half of the chart capacity for that configuration.
    • B.Work may continue if each load's weight is determined and given to the operator before the lift.✓ Answer
    • C.Work may continue with no further action, because an experienced operator can judge load weight by feel.
    • D.All crane operations must stop immediately and may not resume until the device is repaired and recalibrated.

    A load weighing device or load moment indicator is an operational aid, not a safety device, so its failure does not automatically take the crane out of service. The rule permits continued work only under the specified temporary alternative measure — the load weight is established from manufacturer or shipping data or a recognized calculation and given to the operator before the lift — with the repair completed inside the prescribed time.

    Ref QB-AJ79RVSource: OSHA 29 CFR 1926.1416, Operational aids (Category II devices and temporary alternative measures)Report a problem with this question

  3. 3. Which device is a Category I operational aid — the group that must be repaired within the shortest time after a deficiency occurs?

    • A.Anti two-block device✓ Answer
    • B.Outrigger/stabilizer position sensor
    • C.Boom angle indicator
    • D.Hoist drum rotation indicator

    The federal operational-aid rule places only three devices in Category I — the boom hoist limiting device, the luffing jib limiting device and the anti two-block device — because each one guards against an immediate structural or dropped-load failure; these carry the 7-calendar-day repair deadline. Boom angle/radius indicators, jib angle indicators, boom length indicators, load weighing/LMI devices, outrigger position sensors and drum rotation indicators are Category II, with a 30-calendar-day deadline.

    Ref QB-T2DEBWSource: OSHA 29 CFR 1926.1416, Operational aids (Category I and Category II lists)Report a problem with this question

  4. 4. A crane's boom hoist limiting device becomes inoperative and the required temporary alternative measures are put in place. When must the repair be completed?

    • A.No later than 7 calendar days after the deficiency occurs, or after parts arrive.✓ Answer
    • B.At the next annual comprehensive inspection of the equipment.
    • C.Before the end of the work shift, with no exception.
    • D.Within 30 calendar days, or within 30 calendar days after replacement parts arrive.

    The boom hoist limiting device is a Category I operational aid, and the federal rule sets a 7-calendar-day repair deadline for that category, with a single exception: if parts were ordered within those 7 calendar days, the repair must be finished within 7 calendar days of receiving the parts. The same parts exception applies to Category II aids, whose base deadline is 30 calendar days.

    Ref QB-7J598SSource: OSHA 29 CFR 1926.1416, Operational aids (Category I repair deadline)Report a problem with this question

  5. 5. The anti two-block device on a telescopic boom crane has failed and parts are on order. Which temporary measure allows work to continue?

    • A.Mark the hoist cable to give warning, and use a spotter when extending the boom.✓ Answer
    • B.Reeve additional parts of line so that the load block physically cannot reach the boom tip.
    • C.Rely on the load moment indicator, which will alarm before the block reaches the boom tip.
    • D.Restrict all lifts to no more than 75 percent of the chart value for the configuration.

    For a telescopic boom crane the prescribed temporary alternative measure is to clearly mark the hoist cable at a point that gives the operator time to stop the hoist, and to use a spotter when extending the boom, because telescoping out draws the block toward the tip; on a lattice boom crane marking the cable or using a spotter is enough. Extra parts of line and the LMI do nothing to prevent two-blocking, and the device is Category I, so it must still be repaired within the short deadline.

    Ref QB-Q2BETSSource: OSHA 29 CFR 1926.1416, Operational aids (anti two-block device, temporary alternative measures)Report a problem with this question

  6. 6. What distinguishes an anti two-block warning device from an anti two-block prevention device, and which is required when hoisting personnel?

    • A.The prevention device only lights an indicator lamp while the warning device sounds a horn; neither one is required for hoisting personnel.
    • B.The warning device automatically stops the function while the prevention device only alarms; the warning device is the one required for hoisting personnel.
    • C.They are the same device under two names, and either one may be used when hoisting personnel.
    • D.The warning device only alerts the operator, while the prevention device automatically stops the function that would cause two-blocking.✓ Answer

    A two-block warning device gives the operator an alarm and leaves the correction to human reaction, whereas a prevention system interrupts the hoist, telescope or boom function itself before contact can occur. Because a two-block failure over a suspended platform would drop the load line on the occupants, the personnel-hoisting rule requires an automatic prevention device that is functioning, not merely a warning.

    Ref QB-8JGKDTSource: OSHA 29 CFR 1926.1431, Hoisting personnel; 29 CFR 1926.1416, Operational aidsReport a problem with this question

  7. 7. The hoist drum is not turning and the load hangs stationary below the boom tip. Which operator action can still bring the load block up against the boom tip?

    • A.Swinging the upperworks to the right
    • B.Retracting the boom
    • C.Extending (telescoping) the boom out✓ Answer
    • D.Setting the swing brake

    Two-blocking is contact between the load block, hook or overhaul ball and the boom tip assembly, and it does not require hoisting. Telescoping the boom out moves the tip away from the drum, so rope is drawn out of the hanging portion of the line and the block rises toward the tip; boom hoist movement can close the same gap. The result can shear the rope and drop the load, so an anti two-block device or a marked cable and spotter is essential during these functions.

    Ref QB-R2PRYTSource: OSHA 29 CFR 1926.1416, Operational aids; ASME B30.5, Mobile and Locomotive CranesReport a problem with this question

  8. 8. While the operator is telescoping the boom out, the anti two-block alarm sounds. What should the operator do FIRST?

    • A.Continue extending slowly while watching the block, then boom down to finish the move.
    • B.Swing away from the load and set it down in a clear area.
    • C.Stop the function that is closing the gap, then create clearance by paying out line.✓ Answer
    • D.Increase engine speed to complete the extension before the block reaches the tip.

    The alarm means the block is approaching the boom tip, so the only correct first step is to stop the function that is causing the approach; continuing it, or adding another function, keeps closing the gap. Clearance is then restored by reversing the cause — paying out the load line or retracting the boom — because powering through a two-block condition can part the hoist rope and drop the load.

    Ref QB-DJ999ZSource: ASME B30.5, Mobile and Locomotive Cranes; OSHA 29 CFR 1926.1417, OperationReport a problem with this question

  9. 9. Before starting work the operator finds that the crane level indicator is not working. What is required?

    • A.Work may continue at reduced capacity until the next scheduled inspection.
    • B.Work may not begin; the level indicator is a required safety device.✓ Answer
    • C.Work may continue for up to 7 calendar days if a spotter watches the outriggers during each lift.
    • D.Work may continue for up to 30 calendar days as long as the operator checks level with a hand level.

    The crane level indicator is listed as a safety device along with boom stops, jib stops, foot-pedal brake locks, integral holding devices on hydraulic outrigger and stabilizer jacks, rail clamps and the horn. Operations must not begin unless every one of these is in proper working order, and if one fails during operation the operator stops safely and the equipment goes out of service — there are no temporary alternative measures and no repair grace period for safety devices, which is exactly what separates them from operational aids.

    Ref QB-W2FEUZSource: OSHA 29 CFR 1926.1415, Safety devicesReport a problem with this question

  10. 10. The boom angle/radius indicator is inoperative. Which temporary measure allows the crane to keep working?

    • A.Determine the radius or boom angle by physically measuring each configuration.✓ Answer
    • B.Estimate the radius by counting the operator's paces from the crane to the load.
    • C.Substitute the boom length indicator reading for the radius.
    • D.Stop all lifting until the indicator is repaired and recalibrated.

    The boom angle or radius indicator is a Category II operational aid, so work may continue only under its specified temporary measure: the radius or angle is physically measured with a measuring device rather than estimated. Pacing is an estimate, and boom length alone does not give radius, since radius depends on boom angle and on deflection under load; the device must still be repaired within the Category II deadline.

    Ref QB-Q3ESP2Source: OSHA 29 CFR 1926.1416, Operational aids (boom angle or radius indicator, temporary alternative measures)Report a problem with this question

  11. 11. What is the purpose of a hoist drum rotation indicator, and what temporary measure applies if it fails?

    • A.It weighs the load hanging on the line; if it fails, the load weight is taken from shipping papers.
    • B.It counts the parts of line reeved through the load block; if it fails, the operator recounts the parts of line each morning.
    • C.It measures wire rope wear and stretch; if it fails, the rope must be replaced before further use.
    • D.It shows that the drum is turning and which way; if it fails, the drum is marked so rotation can be seen.✓ Answer

    A drum rotation indicator exists because on many machines the operator cannot see the hoist drum from the cab and needs positive confirmation that the drum is moving and in which direction, particularly when starting a lift or lowering. It is a Category II operational aid, and the prescribed temporary measure is to mark the drum so rotation is visible, adding mirrors or video if that is what it takes for the operator to see the mark.

    Ref QB-7K8M42Source: OSHA 29 CFR 1926.1416, Operational aids (hoist drum rotation indicator)Report a problem with this question

  12. 12. Why can starting or stopping a load abruptly overload a crane that is lifting less than its chart capacity?

    • A.Because rated capacities are static values; abrupt motion adds dynamic force.✓ Answer
    • B.Because the chart capacities already include a built-in allowance for shock loading, which is then used up.
    • C.Because sudden movement shifts the load's center of gravity into a lighter position.
    • D.Because the hoist rope stretches under sudden movement, which increases the load radius but not the load.

    Load chart values are static ratings; they do not contain an allowance for the extra force created when a mass is accelerated or decelerated. Snatching a stuck load, taking up slack rope suddenly or stopping a descending load quickly all impose a dynamic force on top of the static weight, which is why smooth control movements and reduced speeds are required rather than optional.

    Ref QB-TUZ3JUSource: ASME B30.5, Mobile and Locomotive Cranes (operating practices, dynamic loading)Report a problem with this question

  13. 13. What happens to a suspended load when the operator swings too fast and then stops the swing abruptly?

    • A.The load becomes effectively lighter because centrifugal force carries part of its weight.
    • B.The load stays directly under the boom tip at all times, so swing speed has no effect on radius.
    • C.The load moves inward toward the crane, shortening the radius and increasing available capacity.
    • D.The load swings outward like a pendulum, increasing radius and reducing capacity.✓ Answer

    A suspended load is a pendulum: swing acceleration throws it outward, and the greater the swing speed the farther out it rides. Because capacity falls as radius grows, the crane can be inside the chart at the pick and outside it in mid-swing, and the out-of-plane position also applies side force to a boom that is designed to carry load vertically. The control is slow, smooth swing starts and stops with the load kept under the boom tip.

    Ref QB-ACUWXTSource: ASME B30.5, Mobile and Locomotive Cranes (operating practices, swinging the load)Report a problem with this question

  14. 14. Why is using a mobile crane to drag a load sideways prohibited even when the load weighs far less than the chart capacity?

    • A.Because the drag force invalidates the load moment indicator's calibration until it is reset.
    • B.Because chart capacities assume dragging is done only with the boom fully retracted and at maximum angle.
    • C.Because dragging wears out the tires or track pads faster than normal travel.
    • D.Because booms are designed to carry load vertically, and side loading can buckle them.✓ Answer

    Boom structures — lattice and telescopic alike — are engineered for load applied along their vertical plane, and the load chart rates only that condition. Dragging a load laterally, or pulling at an angle, introduces a bending and torsional side force that can buckle a lattice boom or damage a telescopic boom's sections long before the chart weight is reached, so the practice is prohibited outright rather than limited by weight.

    Ref QB-SUNRCTSource: ASME B30.5, Mobile and Locomotive Cranes (side loading and dragging prohibited); OSHA 29 CFR 1926.1417, OperationReport a problem with this question

  15. 15. As a load is picked up, what should the operator expect the boom to do, and what is the operational effect?

    • A.The boom deflects downward under load, so the actual loaded radius is greater than the radius measured before the pick.✓ Answer
    • B.The boom rises slightly, shortening the radius, so the available capacity increases as the load leaves the ground.
    • C.The boom twists sideways under load, which is normal on modern cranes and requires no action.
    • D.The boom remains perfectly rigid, and any radius measured before the pick stays valid throughout the lift.

    Every boom deflects when load is applied: the tip drops and moves outward, which increases the operating radius beyond whatever was measured with the hook empty. Since capacity decreases as radius increases, a lift planned at the unloaded radius can be over capacity once the load is off the ground, so the radius must be verified in the actual loaded condition.

    Ref QB-9CGKSSSource: ASME B30.5, Mobile and Locomotive Cranes (determining load radius under load)Report a problem with this question

  16. 16. How does free fall lowering differ from power-controlled lowering, and when is free fall of the load line prohibited?

    • A.Free fall is the safer method because it removes drive-train forces from the boom, and it is prohibited only in high wind.
    • B.In free fall the drum is released and the load descends under gravity with only the brake; it is prohibited when hoisting personnel.✓ Answer
    • C.In free fall the engine drives the drum downward, which gives the most precise placement, and it is prohibited only on rubber tires.
    • D.There is no practical difference between the two; the terms describe the same drum function on different crane types.

    In power-controlled lowering the drive train holds and meters the load down, so speed is controlled at all times; in free fall the drum is declutched and only the brake stands between the load and the ground, which makes overspeed, shock loading when the brake is applied and loss of control far more likely. For that reason the personnel-hoisting rule forbids free fall of the load line and requires boom hoist controls at their most controlled setting.

    Ref QB-RUAE7SSource: OSHA 29 CFR 1926.1431, Hoisting personnel; ASME B30.5, Mobile and Locomotive CranesReport a problem with this question

  17. 17. Which of the following is required for a multi-crane (tandem) lift?

    • A.Nothing beyond confirming that the combined chart capacities of the two cranes exceed the weight of the load.
    • B.That both cranes be of identical type and boom length, after which the standard single-crane procedures apply unchanged.
    • C.A qualified person's plan, a load-share analysis, one signal person and slow, coordinated moves.✓ Answer
    • D.Each operator working independently at full chart capacity, each taking direction from his own signal person.

    In a tandem lift the share of the load carried by each crane changes as the load tilts, as the cranes swing or travel, and as radii change, so the federal rule requires the lift to be planned by a qualified person (or a competent person assisted by one), reviewed with everyone involved, and directed by a lift director. Capacities are commonly reduced below chart values to absorb that uncertainty, one signal person coordinates so the machines move together, and function speeds are kept slow and synchronized.

    Ref QB-8C59MRSource: OSHA 29 CFR 1926.1432, Multiple-crane/derrick lifts; ASME B30.5, Mobile and Locomotive Cranes (multiple crane lifts)Report a problem with this question

  18. 18. When a crane is used to hoist employees on a suspended personnel platform, the total load must not exceed what portion of the crane's rated capacity for that radius and configuration?

    • A.100 percent
    • B.50 percent✓ Answer
    • C.25 percent
    • D.75 percent

    The federal personnel-hoisting rule caps the total load — platform, occupants, tools and rigging — at 50 percent of the rated capacity for the radius and configuration in use, building in a large margin because a failure would injure people rather than damage cargo. The same rule adds a functioning automatic anti two-block prevention device, a proof test of the platform and rigging to 125 percent, a trial lift immediately before the shift, no free fall of the load line, and, when wind (sustained or gusting) exceeds 20 miles per hour at the platform, a qualified person's decision on whether hoisting personnel is still safe.

    Ref QB-QUX32RSource: OSHA 29 CFR 1926.1431, Hoisting personnelReport a problem with this question

  19. 19. How does the operator determine the wind speed at which a particular lift must be stopped?

    • A.A single limit of 20 miles per hour applies to all crane operations regardless of configuration.
    • B.From the manufacturer's operating manual and wind data for the configuration in use.✓ Answer
    • C.A single limit of 30 miles per hour is the accepted industry standard for every mobile crane.
    • D.Whenever the wind indicator alarms, since the alarm point is factory set to the safe limit for any crane.

    Allowable wind is configuration-dependent: a long boom, a jib or a large sail-area load can force a reduction long before a shorter, compact configuration would, so the governing limit is the one published by the manufacturer for the machine as it is rigged. The wind indicator is an operator aid that tells the operator what the wind is doing, not what the crane can stand; the one wind figure fixed by federal rule is the 20 mile-per-hour sustained wind limit for hoisting personnel on a suspended platform.

    Ref QB-7CSWEQSource: ASME B30.5, Mobile and Locomotive Cranes (wind and manufacturer's limitations); OSHA 29 CFR 1926.1431, Hoisting personnelReport a problem with this question

  20. 20. At the end of the shift the operator is shutting the crane down and leaving it unattended. Which procedure is correct?

    • A.Leave the boom at a high angle with the hook block hanging free so the crane is ready to work in the morning.
    • B.Leave the crane secured: land the load, position the boom as specified, set the brakes and locks.✓ Answer
    • C.Leave the engine idling with the controls live so the crane can be repositioned by others if the site needs it.
    • D.Leave the load suspended a short distance off the ground so it is in position for the next shift.

    Securing an unattended crane means removing every stored hazard: the load is landed, the boom is placed where the manufacturer specifies for the machine and the expected weather, swing and travel brakes or locks are set so wind cannot move the machine, controls are neutralized and start-up is disabled against unauthorized use. A suspended load may never be left unattended, and an operator may stay away from the controls with a load suspended only under the narrow conditions the standard specifies.

    Ref QB-C7FYFYSource: OSHA 29 CFR 1926.1417, Operation (leaving equipment unattended, shutdown and securing); ASME B30.5, Mobile and Locomotive CranesReport a problem with this question

  21. 21. A load must be guided as it is swung into place and landed. Which practice is correct?

    • A.Have a worker place a hand on the load and walk beneath it so the load can be felt and steadied all the way down.
    • B.Leave the load suspended and unattended while workers move into the landing area to prepare it.
    • C.Let the load rotate freely and have workers stand directly under it to catch it as it comes down.
    • D.Use a tagline long enough to keep the handler out of the fall zone, never wrapped around the hand or body.✓ Answer

    A tagline controls rotation and swing from outside the fall zone, which is the whole point of using one: no employee is permitted under a suspended load, and only those hooking, unhooking or guiding a load that is under control may be in the fall zone at all. Wrapping the line around the hand or body removes the worker's ability to let go if the load moves unexpectedly, and a suspended load is never left unattended.

    Ref QB-VPM53ZSource: OSHA 29 CFR 1926.1425, Keeping clear of the load; ASME B30.5, Mobile and Locomotive CranesReport a problem with this question

  22. 22. With a load suspended and the crane part-way through a swing, the operator feels the machine go light and the overload alarm sounds. What is the correct immediate response?

    • A.Continue booming out to reach the intended landing point and set the load down.
    • B.Swing quickly to the nearest open area and release the load there.
    • C.Stop, then reduce the load moment by lowering at the shortest safe radius.✓ Answer
    • D.Increase engine speed and hoist the load higher to regain stability.

    Going light and alarming means the crane is at or beyond its capacity for the current radius, so anything that increases radius or shifts the load over a weaker quadrant makes it worse: swinging can move the load over the least stable part of the machine and booming out lengthens the lever arm. The reflex is to stop, then unload the machine by shortening the radius — boom up or retract — or by lowering the load vertically to the ground at the shortest safe radius, and only then investigate the weight and setup.

    Ref QB-B74NAXSource: ASME B30.5, Mobile and Locomotive Cranes (operating practices, overload and loss of stability); OSHA 29 CFR 1926.1417, OperationReport a problem with this question

  23. 23. A crew will be hoisted on a suspended personnel platform for three days, using the same crane setup and the same lift route. When must the trial lift be made?

    • A.Once at the start of the job, unless the crane is moved
    • B.Once a week, as long as the same operator runs the crane
    • C.Right before each shift in which personnel will be hoisted✓ Answer
    • D.Only after the platform has been repaired or modified

    OSHA requires the trial lift, with the unoccupied platform loaded at least to the anticipated lift weight, immediately before each shift in which personnel will be hoisted. It must also be repeated whenever the crane is moved and set up again or the lift route changes, so an unchanged setup does not let one trial lift cover several shifts. Repair or modification of the platform triggers a new proof test, which is a separate requirement.

    Ref QB-UP9TVXSource: OSHA 29 CFR 1926.1431(h)(1)-(2), Hoisting personnel: trial lift and inspectionReport a problem with this question

  24. 24. Before employees are hoisted at a new jobsite, the personnel platform and its rigging must be proof tested. What does that test require?

    • A.125% of the platform's rated capacity, held suspended at least 5 minutes✓ Answer
    • B.125% of the crane's rated capacity, held suspended at least 5 minutes
    • C.100% of the platform's rated capacity, held suspended at least 1 minute
    • D.150% of the platform's rated capacity, lifted and lowered without stopping

    The proof test checks the platform and rigging, so the test load is 125% of the platform's own rated capacity, not the crane's. The platform is lowered by controlled load lowering, braked, and held suspended for at least five minutes with the test load evenly distributed, then inspected. It is required at each jobsite before personnel are hoisted and after any repair or modification, and it may be done together with the trial lift.

    Ref QB-E76NT2Source: OSHA 29 CFR 1926.1431(j)(1)-(2), Hoisting personnel: proof testingReport a problem with this question

  25. 25. Workers will be hoisted in a personnel platform at a new work location. Which description of the required pre-lift meeting is correct?

    • A.Held after the trial lift; only the operator and the lift director need attend
    • B.Held once per project; only the employees who will ride in the platform attend
    • C.Held before the trial lift; operator and signal person attend, riders are briefed later
    • D.Held before the trial lift; operator, signal person, riders and task supervisor attend✓ Answer

    The pre-lift meeting exists so everyone involved reviews the personnel-hoisting requirements and the procedures to be followed before anyone leaves the ground. OSHA requires it to be attended by the operator, the signal person if one is used, the employees to be hoisted, and the person responsible for the task. It is held before the trial lift at each new work location and repeated for any employee newly assigned to the operation.

    Ref QB-XPBTD3Source: OSHA 29 CFR 1926.1431(m)(1)-(3), Hoisting personnel: pre-lift meetingReport a problem with this question

  26. 26. The operator must lower a load to the bottom of a deep shaft, well below the crane's setup level. As the hook nears the bottom, how much rope must still remain on the hoist drum?

    • A.At least one full wrap, since the rope is clamped at the drum
    • B.At least two full wraps, with the load at its lowest point✓ Answer
    • C.No set minimum, as long as the drum anchor is secure
    • D.At least five full wraps, but only when hoisting personnel

    Neither the load nor the boom may be lowered below the point where fewer than two full wraps of rope remain on their drums. The drum anchor is not designed to carry the full line pull; the friction of the remaining wraps takes most of the load off it, so running the drum nearly empty can pull the rope free. The same two-wrap minimum governs whether a rope can be shortened after damage is cut out.

    Ref QB-D7TANZSource: OSHA 29 CFR 1926.1417(t), Operation (two full wraps on drums); 29 CFR 1926.1413(a)(4)Report a problem with this question

  27. 27. A qualified person is performing the annual/comprehensive inspection of a mobile crane. Beyond the shift-inspection items, what must be checked on the sheaves and drums?

    • A.Groove size, but only when the wire rope is being replaced
    • B.Only noise during a no-load run, since cracks cannot be seen
    • C.Only rope lubrication, since the sheaves are covered by guards
    • D.Cracks or significant wear on the sheaves and on the drums✓ Answer

    The annual/comprehensive inspection repeats the shift-inspection items and adds a list of structural and mechanical checks, including sheaves and drums for cracks or significant wear. A cracked or badly worn sheave or drum groove can damage the rope and fail under load, so guards or a quiet no-load run are no reason to skip a direct look. Any deficiency found must be evaluated by the qualified person to decide whether it is a safety hazard.

    Ref QB-WPYF82Source: OSHA 29 CFR 1926.1412(f)(1)-(2)(ii), Inspections: annual/comprehensive (sheaves and drums)Report a problem with this question

  28. 28. During a lift directed by a qualified signal person, a laborer who is not part of the lift crew sees a tag line snag and gives the emergency stop signal. What should the operator do?

    • A.Continue, because only the assigned signal person may signal
    • B.Stop, because a stop signal from anyone must be obeyed✓ Answer
    • C.Pause only after the signal person repeats the stop signal
    • D.Finish landing the load first, then stop to check the snag

    OSHA says anyone who becomes aware of a safety problem must alert the operator or signal person by giving the stop or emergency stop signal, and the operator must obey it. The rule exists because the person who sees a hazard is often not the designated signal person, and waiting for confirmation or finishing the move costs the seconds that matter. Other signals still come only from the assigned signal person.

    Ref QB-G7VA65Source: OSHA 29 CFR 1926.1417(y), Operation (stop or emergency stop signal from anyone)Report a problem with this question

Other topics in this exam

Practice questions based on the published NCCCO mobile crane operator exam outlines and the consensus safety practices the trade runs on. CCO and NCCCO are marks of the National Commission for the Certification of Crane Operators; this site is not affiliated with or endorsed by NCCCO. Capacity always comes from the load chart for the machine and configuration in front of you, and wind, ground-bearing and permit limits are set by the manufacturer's manual and the authority having jurisdiction — never from a practice question. Confirm current exam requirements before testing. About CCO certification →