← Back

41 Process (Technical PM) Practice Questions & Answers

Every Process (Technical PM) practice question from the PMP Practice Test, with the correct answer and a short explanation.

Start practice test
  1. 1. A bank is launching a mobile lending product. The regulatory reporting module is fixed by law and will be audited before release; the customer-facing app screens are expected to change repeatedly as usability testing feeds back. The sponsor asks the project manager to name one delivery approach for the whole programme. What should the project manager recommend?

    • A.A hybrid approach that baselines the regulatory module predictively while the app screens run from an iterative backlogAnswer
    • B.An adaptive approach across both streams, because a single cadence keeps the two teams synchronised and simplifies reporting
    • C.A predictive approach now, converting the app stream to iterations only after the regulatory module passes its audit
    • D.A predictive approach across both streams, because the regulatory audit sets a fixed release date the whole programme must meet

    Delivery approach is tailored to the characteristics of the work, not imposed uniformly. A stream with stable, legally fixed requirements and a single audited release fits predictive control, while a stream with emergent requirements and a live feedback loop fits iterative delivery. Forcing either approach across both streams sacrifices the strength one stream needs, so the project manager recommends tailoring stream by stream.

    Source: PMP Examination Content Outline, Process Task 1 (recommend a development approach based on project needs, complexity and magnitude); PMBOK Guide tailoringReport a problem with this question

  2. 2. Halfway through a predictive infrastructure project, a supplier announces that the specified network hardware will be discontinued, so a different model must be used. The integrated project management plan, schedule and cost baseline all assume the original model. What is the project manager's most appropriate action?

    • A.Reissue the integrated plan around the new model and inform stakeholders that the baselines have been updated
    • B.Analyse the impact on scope, schedule and cost and take the revision through the established plan-update pathAnswer
    • C.Hold the original plan intact and absorb the difference from the management reserve the sponsor set aside
    • D.Direct the team to install the replacement model now and record the substitution in the lessons learned repository

    The integrated plan is a living artifact, but it is maintained through a defined path rather than rewritten at the project manager's discretion. New information triggers impact analysis first, so the decision makers see what the substitution does to scope, schedule and cost before any baseline moves. Acting on the change first, or reissuing baselines unilaterally, removes the governance that protects the baseline's meaning.

    Source: PMP ECO Process Task 1 (create and maintain the integrated project management plan); baseline maintenance doctrineReport a problem with this question

  3. 3. A project manager decomposes an approved scope statement into a work breakdown structure. A team lead proposes adding a package for a monitoring dashboard the customer mentioned wanting someday but which does not appear in the scope statement, arguing it will be cheap to build alongside the other work. How should the project manager respond?

    • A.Keep the dashboard out and instead widen an existing package's description so the team can build it quietly
    • B.Keep the dashboard out of the structure, since it must decompose the approved scope and only that scopeAnswer
    • C.Include the dashboard but tag it as optional work to be dropped if the schedule later comes under pressure
    • D.Include the dashboard as a low-priority package so the customer receives extra value at negligible cost

    The work breakdown structure obeys the 100% rule: it captures all of the work required by the approved scope and only that work. Building something the customer did not request is gold plating, and it consumes budget and effort that were never authorised, whatever its apparent cost. A genuine desire for the dashboard is handled by taking it through the change path so it can be evaluated and approved.

    Source: PMP ECO Process Task 2 (break down scope); WBS 100% rule and prohibition on gold platingReport a problem with this question

  4. 4. An agile team finishes a sprint. Every story meets its acceptance criteria and passes the automated test suite, and the team's definition of done is satisfied. The product owner has not yet reviewed the increment. What must still happen before the increment can be treated as accepted?

    • A.The team runs a further round of regression testing to confirm the automated suite did not miss defects
    • B.The team demonstrates the increment at the retrospective so improvement actions can be agreed alongside sign-off
    • C.The project manager records the increment as accepted, since the definition of done is the agreed acceptance rule
    • D.The product owner formally accepts the increment, since passing internal checks is not customer acceptanceAnswer

    Controlling quality and validating scope are different activities with a fixed order: internal verification confirms the deliverable is correct, and only then does the authorised customer representative formally accept it. The definition of done and a green test suite are internal correctness checks. Acceptance belongs to the product owner, and it happens in the review, not in the retrospective, which examines the team's process.

    Source: PMP ECO Process Task 2 (obtain stakeholder agreement on scope); validate scope follows control qualityReport a problem with this question

  5. 5. A project manager must estimate a work package for a data migration. The organisation has completed four very similar migrations, and detailed records exist of hours per table migrated for each of them. The team also has enough time to break the package down task by task. Which estimating choice best fits this situation?

    • A.Estimate analogously from the most recent migration, since four comparable projects make the analogy reliable
    • B.Estimate with a three-point range per task, since prior migrations still varied in how long they took
    • C.Estimate parametrically from the rate per table alone, since detailed records outrank any team-level judgement
    • D.Estimate bottom-up from the decomposed tasks and use the historical rate per table to sanity-check the totalAnswer

    The estimating technique is chosen from the information actually available and the time available to estimate. Here the work can be decomposed and the team has time, which makes bottom-up the most accurate route, while the historical rate per table provides an independent parametric cross-check on the result. Analogous estimating is the top-down fallback used when detail is missing, so it wastes the detail this project already has.

    Source: PMP ECO Process Task 8 (estimate project tasks; use benchmarks and historical data); estimating technique selectionReport a problem with this question

  6. 6. A predictive project is four weeks behind on the critical path. The customer's contract carries penalties for late delivery, funds are available in the budget, and the remaining critical activities have genuine finish-to-start dependencies driven by physical curing times. Which compression choice fits this situation?

    • A.Reduce the scope of the remaining critical activities so the curing steps can be shortened without added cost
    • B.Crash the critical activities by adding resources, accepting the added cost the available funds can coverAnswer
    • C.Fast track the critical activities by overlapping them, accepting the rework risk the schedule pressure justifies
    • D.Level resources across the critical path so the four-week slip is absorbed within the available total float

    Crashing adds resources to shorten critical activities and raises cost, while fast tracking overlaps activities and raises the risk of rework. Fast tracking is only available where a dependency is discretionary, and a physical curing time is a mandatory dependency that cannot be overlapped. With funds available and a penalty for lateness, paying for compression is the trade-off that fits.

    Source: PMP ECO Process Task 8 (analyze schedule variation); schedule compression: crashing vs fast tracking, mandatory vs discretionary dependenciesReport a problem with this question

  7. 7. A status dashboard for a construction project reports a cost performance index of 0.85 and a schedule performance index of 1.05 at the midpoint. The sponsor asks what these two figures together say about the project. What is the correct reading?

    • A.Work is ahead of schedule but each unit of work costs more than planned, so the budget is erodingAnswer
    • B.Work is on budget but ahead of schedule, so the cost figure reflects front-loaded spending rather than overrun
    • C.Work is behind schedule and over budget, so both the cost and the schedule baselines are being breached
    • D.Work is ahead of schedule and the cost overrun will be recovered as the early finish reduces overheads

    The cost performance index compares earned value with actual cost, so a value below one means the project is getting less value than it is paying for and is over budget. The schedule performance index compares earned value with planned value, so a value above one means more work has been earned than planned and the project is ahead. Reading them together gives the diagnosis of an ahead-of-schedule project that is spending inefficiently.

    Source: PMP ECO Process Task 6 (monitor financial variations); earned value: CPI = EV/AC, SPI = EV/PVReport a problem with this question

  8. 8. During execution, an identified risk that the team had analysed and funded materialises, and responding to it will cost money. The project manager confirms the amount needed is within the allowance set aside for that risk. What should the project manager do?

    • A.Request access to the management reserve from the sponsor, since any unplanned spending needs governance approval
    • B.Re-baseline the cost budget upward by the amount required, since the response was not in the original activity estimates
    • C.Draw on the contingency reserve under their own authority, since it sits inside the cost baseline for identified risksAnswer
    • D.Absorb the cost within the affected work package's estimate, since reserves are released only at the end of a phase

    Contingency reserve funds identified risks, sits inside the cost baseline, and is under the project manager's control, so no separate approval is needed to use it for the risk it was calculated against. Management reserve covers unknown-unknowns, sits outside the cost baseline in the project budget, and requires sponsor or governance approval. Using the reserve as designed also means no re-baselining is triggered.

    Source: PMP ECO Process Task 6 (manage financial reserves); cost baseline = estimates + contingency; project budget = cost baseline + management reserveReport a problem with this question

  9. 9. A software project's defect rate keeps rising, and the team spends a growing share of each iteration fixing defects found after code is merged. The quality manager proposes doubling the size of the test team to catch more defects before release. What should the project manager advocate instead?

    • A.Track the defect rate against a control chart each iteration so the team can see when the process drifts out of control
    • B.Add appraisal capacity as proposed, since finding defects earlier in testing is the cheapest way to reduce failure cost
    • C.Tighten the acceptance criteria applied at release so defective builds are rejected before they reach the customer
    • D.Strengthen prevention through peer review and automated checks at merge, so defects are not created in the first placeAnswer

    The cost of quality distinguishes conformance costs, which are prevention and appraisal, from nonconformance costs, which are internal and external failure. Prevention is consistently cheaper than failure, and adding inspection capacity only finds defects that have already been built and paid for. Quality is planned in rather than inspected in, so the response attacks the mechanism creating the defects.

    Source: PMP ECO Process Task 7 (manage cost of quality); cost of quality: prevention over inspectionReport a problem with this question

  10. 10. A team's sprint burndown was tracking close to the ideal line, then flattened for several days while the team reported completing work daily and no one was absent. The project manager reviews the board before the next daily meeting. What is the most likely explanation to investigate first?

    • A.Work was added to the sprint, so completed points are being offset by newly introduced scopeAnswer
    • B.The team's velocity estimate was too low, so the remaining work was overstated from the start of the sprint
    • C.The team stopped updating the board, so completed work is simply not being reflected in the chart
    • D.Stories are being finished but held unaccepted, so the product owner's review queue is masking real progress

    A burndown plots remaining work against time, so a flat line means remaining work is not falling. When the team is genuinely completing items every day, the remaining total can only hold steady if new work is entering the sprint at roughly the rate work is finished. The other explanations would show as a stalled or unchanged board rather than as steady completion against a flat line.

    Source: PMP ECO Process Task 9 (measure, analyze and update metrics); burndown chart interpretationReport a problem with this question

  11. 11. An organisation needs a specialist to build an integration whose requirements are still emerging and are expected to be refined with the vendor over several months. The procurement lead proposes a firm fixed-price contract to protect the budget. What should the project manager recommend?

    • A.A firm fixed-price contract as proposed, since it transfers the cost risk of the emerging scope to the vendor
    • B.A time and materials arrangement with a not-to-exceed ceiling, matching the uncertainty while capping exposureAnswer
    • C.A fixed price with economic price adjustment, since the multi-month duration exposes the deal to rate changes
    • D.A cost plus award fee contract, since the buyer can then judge vendor performance subjectively each period

    Contract type is matched to how well the scope is defined, because that is what determines where risk can fairly sit. Fixed price requires a well-defined scope; laying it over an evolving scope drives change disputes and padded bids rather than protecting the budget. Time and materials suits uncertain, specialist work of limited size, and a not-to-exceed ceiling supplies the budget protection the procurement lead is seeking.

    Source: PMP ECO Process Task 5 (select preferred contract types); contract type risk allocation and scope certaintyReport a problem with this question

  12. 12. A sponsor is impatient because a twelve-month product build has produced nothing usable in five months, and market conditions may shift. The backlog is prioritised but the team plans a single release at the end. What should the project manager propose?

    • A.Release the highest-value increment early so benefits start accruing and market feedback can steer the remainderAnswer
    • B.Compress the remaining schedule so the single release lands sooner and the market window is less likely to close
    • C.Add interim milestone demonstrations to the schedule so the sponsor can see progress without changing the release plan
    • D.Reprioritise the backlog so the riskiest technical items are built first and the schedule uncertainty falls fastest

    Value-based delivery asks whether benefits can be realised earlier rather than held until a terminal release. Shipping the highest-value increment starts the benefit stream, exposes the product to real market feedback while there is still time to act on it, and reduces the risk that twelve months of work meets a changed market. Demonstrations and compression address the sponsor's visibility and timing but deliver no benefit any sooner.

    Source: PMP ECO Process Task 3 (assess opportunities to deliver value incrementally)Report a problem with this question

  13. 13. A project manager is planning a two-year programme whose first six months are well understood and whose later phases depend on decisions not yet taken. Stakeholders press for a fully detailed schedule for all twenty-four months before approval. How should the project manager respond?

    • A.Defer schedule approval entirely until the outstanding decisions are taken, so only one baseline is ever issued
    • B.Produce the full detailed schedule requested, since stakeholders cannot approve a plan whose later phases are vague
    • C.Detail the near-term work and set the later phases as fixed milestone dates so stakeholders have firm commitments
    • D.Detail the near-term work and keep later phases at a higher level, elaborating them as the decisions are madeAnswer

    Planning is done to the level of detail the available information supports, a practice known as progressive elaboration or rolling wave planning. Detailing work that depends on undecided inputs produces precision that is false and that will be reworked, while refusing to plan at all leaves the near-term work unmanaged. Committing to firm dates for undecided phases makes the same error as full detail, only more visibly.

    Source: PMP ECO Process Task 1 and Task 8 (prepare a schedule based on the selected development approach); progressive elaboration and rolling wave planningReport a problem with this question

  14. 14. An adaptive team consistently pulls stories into an iteration and then stalls partway because a dependency or an unanswered question surfaces after work has started. The team asks the project manager how to stop this pattern. What should the project manager suggest?

    • A.Agree a stricter definition of done so incomplete stories cannot be counted at the end of the iteration
    • B.Agree a definition of ready so a story is only pulled once its dependencies and questions are resolvedAnswer
    • C.Pull fewer stories into each iteration so the team has slack to resolve dependencies as they surface
    • D.Refine the backlog at the end of each iteration so estimates reflect what the team learned while stalled

    A definition of ready is the entry gate for an iteration: it states the conditions a backlog item must satisfy before the team commits to it, which is exactly where unresolved dependencies and open questions should be caught. A definition of done is the exit gate and does nothing to prevent unready work being pulled. Reducing load or refining later treats the symptom while leaving the entry gate open.

    Source: PMP ECO Process Task 2 (break down scope; backlog refinement); definition of ready as iteration entry criteriaReport a problem with this question

  15. 15. A project manager needs requirements from three hundred field staff spread across many sites, plus deep detail from six subject matter experts who each hold part of a complex approval workflow. Time for elicitation is limited. Which combination of techniques best fits?

    • A.A facilitated workshop for a sample of field staff and document analysis of the experts' written procedures
    • B.A questionnaire for the field staff and a facilitated workshop that brings the six experts togetherAnswer
    • C.Observation of the field staff at work and separate one-to-one interviews with each of the six experts
    • D.Individual interviews with the field staff and a questionnaire circulated to the six experts

    Elicitation techniques are chosen from the number of sources and the kind of information needed. Questionnaires reach a large, dispersed population quickly, which suits three hundred field staff under time pressure. A facilitated workshop suits a small group whose knowledge must be reconciled, because the experts resolve the handoffs in the approval workflow between them rather than each describing a fragment separately.

    Source: PMP ECO Process Task 2 (define scope); requirements elicitation technique selectionReport a problem with this question

  16. 16. A project manager reviews a network diagram with two paths to the final milestone. Path A totals sixty days with zero total float; path B totals fifty-two days. An activity on path B is delayed by five days. What is the effect on the project finish date?

    • A.The finish date slips by three days, because the delay consumes the difference between the two path lengths
    • B.The finish date is unchanged, because path B still has float remaining after absorbing the five-day delayAnswer
    • C.The finish date is unchanged, because delays are only measured against the baseline at the end of the phase
    • D.The finish date slips by five days, because any delay to an activity pushes the milestone it feeds

    The critical path is the longest path through the network and has zero total float, so it sets the project duration. Path B is eight days shorter, giving its activities eight days of total float, and a five-day delay consumes part of that float without extending the network's longest path. Only a delay that exceeds the float, or any delay on the critical path itself, moves the finish date.

    Source: PMP ECO Process Task 8 (analyze schedule variation); critical path is the longest path with zero total floatReport a problem with this question

  17. 17. Two critical activities are each scheduled for one specialist welder, but only one welder is available and the schedule assumed two. The project manager applies resource levelling to resolve the conflict. What should the project manager expect as a result?

    • A.The schedule stays the same length because levelling works only within the float already in the network
    • B.The schedule stays the same length because levelling reassigns work rather than moving activity dates
    • C.The schedule shortens because levelling removes the idle time between the two welding activities
    • D.The schedule may lengthen and the critical path may change, since activities are moved to match availabilityAnswer

    Resource levelling adjusts start and finish dates so demand never exceeds the resources actually available, which can push activities out, extend the overall duration and shift which path is longest. Resource smoothing is the technique that stays within available float and leaves the critical path untouched, but it cannot resolve a hard shortage of the kind described here.

    Source: PMP ECO Process Task 4 (manage and optimize resource needs and availability); resource levelling vs smoothingReport a problem with this question

  18. 18. A manufacturing project's control chart for a machined dimension shows every measurement inside the control limits, but the last eight consecutive points all fall on the same side of the mean. Nothing has been rejected by inspection. What should the project manager conclude?

    • A.The process is performing acceptably, since every measurement remains inside the calculated control limits
    • B.The measurements are being recorded incorrectly, since a genuine process cannot produce eight points in a row
    • C.The process is drifting and should be investigated now, since a consecutive run signals a non-random causeAnswer
    • D.The control limits are set too wide and should be tightened to match the customer's specification limits

    A control chart detects out-of-control conditions in two ways: points beyond the control limits, and non-random patterns within them. A run of consecutive points on one side of the mean, commonly called the rule of seven, indicates a systematic cause acting on the process even though nothing has yet breached a limit. Acting on the signal is prevention, whereas waiting for a rejected part is failure cost.

    Source: PMP ECO Process Task 7 (conduct ongoing quality reviews); control chart rule of seven, control limits vs specification limitsReport a problem with this question

  19. 19. A hybrid programme's steering group asks for a single status view covering a regulated hardware stream running to a baseline and a software stream running in iterations. What should the project manager include in the reporting?

    • A.Throughput measures for both streams, since empirical delivery data is more current than baseline variance
    • B.Baseline variance measures for the hardware stream and throughput measures for the software stream, shown togetherAnswer
    • C.Baseline variance for the hardware stream and a narrative summary of the software stream, avoiding mixed metrics
    • D.Baseline variance measures for both streams, so the steering group compares the two on one consistent scale

    Metrics are tailored to the delivery approach each stream actually uses, because a measure only means something against the way the work is planned. Variance against a baseline is meaningful where a baseline exists, and throughput or velocity is meaningful where work is pulled iteratively. Forcing one metric family across both streams produces numbers that misdescribe at least one stream, and replacing one stream's metrics with narrative removes the evidence the steering group needs.

    Source: PMP ECO Process Task 9 (develop project metrics; identify and tailor needed artifacts)Report a problem with this question

  20. 20. A project's final deliverables have been completed and verified, and the customer has issued written acceptance. Two subcontracts remain open and the team is being asked for on other projects. What should the project manager do next?

    • A.Transition the deliverables to the operations team, leaving the subcontracts to be settled by the procurement office
    • B.Close the two subcontracts before releasing the team, since procurement closure precedes administrative releaseAnswer
    • C.Release the team to the other projects first, since the accepted deliverables mean the work itself is finished
    • D.Archive the project records and update the lessons learned repository before touching the open subcontracts

    Closure follows an order that protects the organisation: work is completed and verified, formal acceptance is obtained, procurements are closed, resources are released, records are archived, and the product transitions to operations. Closing the subcontracts requires the team members who can confirm the sellers met their agreements, so releasing people first can leave claims unresolved and evidence unavailable.

    Source: PMP ECO Process Task 10 (conclude closing activities: procurement, financials and resources); closure sequenceReport a problem with this question

  21. 21. Six months into a two-year predictive project, a competitor releases a product that removes most of the demand the business case assumed. The remaining scope can still be delivered on time and on budget. What should the project manager do?

    • A.Reprioritise the remaining scope toward features the competitor lacks, then report the revised plan to governance
    • B.Continue delivering the approved scope on plan, since the project manager is accountable for the agreed baselines
    • C.Raise the eroded business case through governance so a continue, pivot or terminate decision can be takenAnswer
    • D.Commission market research to quantify the lost demand before informing anyone that the case has weakened

    Business value is examined throughout the project, not only at initiation, and delivering scope on time and on budget is not success if the benefits no longer justify the investment. When the business case erodes, the continue, pivot or terminate decision belongs to governance rather than to the project manager, so the correct action is to surface the evidence to the people who own that decision. Changing direction first, or delaying disclosure for research, spends more of the organisation's money on an unexamined case.

    Source: PMP ECO Process Task 3 (examine business value throughout the project); benefits management and governance decision authorityReport a problem with this question

  22. 22. A project's stakeholders span three time zones: a regulator that requires formal evidence of compliance, an operations manager who wants to hear only about exceptions, and a sponsor who expects a weekly summary. The project manager inherits a communications approach that sends one identical report to everyone. What should the project manager do FIRST?

    • A.Ask the sponsor to settle on one reporting format that all of the stakeholder groups will accept.
    • B.Keep the single report but raise its frequency so that every group receives the detail it wants sooner.
    • C.Analyze each group's information needs, timing and preferred format before changing the distribution.Answer
    • D.Publish every project artifact to a shared repository and let each stakeholder pull what it needs.

    Communication planning begins with a stakeholder-by-stakeholder analysis of what information each party needs, when, in what form and from whom; the plan is then tailored to those needs. A single uniform report treats a regulator and an exception-only reader as the same audience, so it simultaneously buries one and starves the other, and sending it more often only multiplies that failure.

    Source: PMP Examination Content Outline (2026), People domain Task 8 — Plan and manage communication (define a communication strategy from stakeholder needs)Report a problem with this question

  23. 23. Two days before a release a defect surfaces that may force a scope decision, and the vendor lead and the product owner disagree about how serious its impact is. A decision is needed today. What should the project manager do FIRST?

    • A.Post the defect analysis on the project dashboard so that each party reviews it when convenient.
    • B.Escalate the disagreement to the steering committee so an authority above both parties rules on it.
    • C.Bring both parties into a short working session today so the decision is reached face to face.Answer
    • D.Send both parties a written analysis of the options and ask each for a reply by the end of the day.

    Interactive communication allows immediate exchange, clarification and agreement, which is why it is the right method for urgent or contested matters. Push communication such as email confirms only that a message was sent, and pull communication such as a dashboard suits large audiences and non-urgent detail; escalation is premature while facilitating the decision is still within the project manager's own authority.

    Source: PMP Examination Content Outline (2026), People domain Task 8 — communication methods: interactive, push and pullReport a problem with this question

  24. 24. A co-located team's task board has not been updated for over a week; members track their own work in personal spreadsheets and the daily meeting runs from memory. What should the project manager do FIRST?

    • A.Replace the physical board with a tool that pulls the status automatically from those spreadsheets.
    • B.Ask the team why the board stopped matching reality and address the cause that they identify.Answer
    • C.Make a board update a condition of any task counting as done and check that at the daily meeting.
    • D.Update the board each morning from the members' spreadsheets so stakeholders see accurate status.

    An information radiator works only while it is the team's own single visible view of the work, so a stale board means the team is getting no value from it. Maintaining it for them, automating it from private records or policing it all leave the team coordinating from spreadsheets, whereas finding the cause with the team is what restores transparency.

    Source: PMP Examination Content Outline (2026), Process domain Task 9 — evaluate project status; information radiators and artifact accessibilityReport a problem with this question

  25. 25. A weekly two-hour project meeting with fifteen attendees regularly ends without a decision being taken, and several of those attending work on unrelated laptops throughout it. What should the project manager do FIRST?

    • A.Halve the meeting to one hour and ask the attendees to close their laptops during the session.
    • B.Define the decisions the meeting exists to produce and invite only the people needed for them.Answer
    • C.Cancel the meeting and send the same distribution list a written status report every week.
    • D.Rotate the facilitator role among the attendees so that each of them has a reason to engage.

    A meeting is justified by the decisions or the collaboration it produces, so the repair starts with its purpose and the participants that purpose requires; duration, ground rules and facilitation follow from that. Halving the time or rotating facilitators leaves a purposeless meeting in place, and cancelling it replaces an interactive need with a push report that cannot produce a decision.

    Source: PMP Examination Content Outline (2026), People domain Task 8 — promote transparency and collaboration; meeting management practiceReport a problem with this question

  26. 26. A sponsor tells the project manager to keep the message positive for the steering committee, but the current forecast shows the delivery date slipping by six weeks. What should the project manager do FIRST?

    • A.Present the forecast to the steering committee unchanged, because transparency outranks the request.
    • B.Report the period as on track and disclose the slip once a recovery plan has been proven to work.
    • C.Ask the project management office to take the schedule forecast to the committee on his behalf.
    • D.Meet the sponsor privately with the forecast, its causes and the options, ahead of the committee.Answer

    Stakeholders are owed accurate information, but the first move is the direct conversation: it surfaces why the sponsor is resisting and lets the two of them face the committee with data and options rather than a surprise. Going straight to the committee, softening the report or handing the message to the project management office all skip the conversation that would have resolved the conflict.

    Source: PMP Examination Content Outline (2026), People domain Task 8 — create reports aligned with sponsor and stakeholder expectations; establish a feedback loopReport a problem with this question

  27. 27. Two teams are working from different versions of the schedule after one of them downloaded a copy weeks ago and kept editing it, and their status reports now show conflicting deliverable dates. What should the project manager do FIRST?

    • A.Identify which schedule is the controlled version and point both teams back to that single source.Answer
    • B.Merge the two schedules into one combined version and ask the sponsor to approve it as the baseline.
    • C.Raise a change request for the differing dates so that the change control board decides them.
    • D.Have each team reconcile its own dates and bring an agreed set to the next status meeting.

    Configuration management exists so that everyone works from one identified, version-controlled copy of an artifact; restoring that single source is what stops the divergence, and only afterwards can any genuine date change be assessed. Merging uncontrolled copies, delegating the reconciliation or sending an unanalyzed difference to the board all treat the symptom.

    Source: PMP Examination Content Outline (2026), Process domain Task 9 — ensure artifacts are updated, documented and accessible; configuration and version controlReport a problem with this question

  28. 28. A short internal project inherits the organization's full library of fourteen document templates, and the team is now spending more effort on the documents than on the work itself. What should the project manager do FIRST?

    • A.Assign one team member to maintain the fourteen documents so the others can focus on delivery.
    • B.Complete all fourteen templates, since organizational process assets are mandatory project inputs.
    • C.Drop the documents the team finds least useful and reinstate any that an auditor later asks for.
    • D.Assess which artifacts the work and the governance really need and tailor the set with the office.Answer

    Tailoring is expected of a project manager: the artifact set is chosen for the size, complexity and governance context of the project rather than applied whole from a template library. Making that choice with whoever owns the governance keeps the documents that serve a real need and retires the rest by agreement instead of by quiet abandonment.

    Source: PMP Examination Content Outline (2026), Process domain Task 9 — identify and tailor the artifacts needed for the projectReport a problem with this question

  29. 29. A Kanban team of six has eleven items in progress, cycle time has doubled, and items sit for days in the ready-for-test column. A stakeholder now asks the team to start one more urgent item. What should the project manager do FIRST?

    • A.Split the team so that half finish the current items while the others begin the urgent request.
    • B.Work with the team to pull the testing queue down before any further item is started at all.Answer
    • C.Add the urgent item to the board and ask the team to work it ahead of the items already started.
    • D.Raise the work-in-progress limit for now so that the urgent item does not breach the policy.

    Work-in-progress limits exist because started-but-unfinished work lengthens cycle time, ties up capacity and hides defects while delivering nothing, so the queue in front of the constraint is emptied before new work is pulled. Starting more, splitting the team or lifting the limit each add to the congestion that has already doubled cycle time.

    Source: PMP Examination Content Outline (2026), Process domain Task 8 — manage schedule and flow; Kanban WIP limits and Little's LawReport a problem with this question

  30. 30. A supplier's interface component on the critical path is now forecast to arrive two weeks late, and a downstream team is already sitting idle. What should the project manager do FIRST?

    • A.Crash the downstream activities with extra staff so that the two weeks are recovered later on.
    • B.Fast track the work by starting integration testing against the current interface specification.
    • C.Confirm the supplier's revised date and analyze its effect on the network and downstream work.Answer
    • D.Log an issue and escalate the delay to the sponsor as a failure of the supplier to perform.

    Compression, escalation and workarounds all depend on facts the project manager does not yet hold, so the delay is confirmed and its schedule effect analyzed first; a late activity may or may not move the finish date once float and near-critical paths are examined. Only then is a response selected, and if it changes a baseline it goes through change control.

    Source: PMP Examination Content Outline (2026), Process domain Task 8 — analyze schedule variation; dependency and critical path analysisReport a problem with this question

  31. 31. The project's cutover weekend has just been found to collide with the operations department's quarter-end financial close, and both activities need the same environment. What should the project manager do FIRST?

    • A.Hold the cutover date and ask operations to postpone the quarter-end close by one week.
    • B.Ask the sponsor to rule on which of the two activities has priority for that environment.
    • C.Meet the operations manager to map both windows and find a slot that protects each of them.Answer
    • D.Move the cutover to the next free weekend and update the schedule baseline accordingly.

    Projects run inside an operating organization, so interdependencies with operations and with other projects are coordinated jointly before anybody's date moves. Overriding operations, rebaselining unilaterally or escalating a conflict that the two managers can resolve between them each bypass the coordination the situation actually calls for.

    Source: PMP Examination Content Outline (2026), Process domain Task 8 — coordinate project activities with other projects and with operationsReport a problem with this question

  32. 32. At the daily stand-up each member reports to the project manager, the project manager then assigns the day's work, and blockers are noted to be looked at later. The meeting now runs thirty-five minutes. What should the project manager do FIRST?

    • A.Let the team run it to coordinate with each other, and take the blockers away to be cleared.Answer
    • B.Keep the present format but cap it at fifteen minutes and move the remaining reports to writing.
    • C.Have the members report only exceptions so that routine items stop consuming the time.
    • D.Replace the stand-up with a written daily update so that the team spends the time on delivery.

    A stand-up is the team's own short planning and coordination event, in which members synchronize with each other and raise impediments; once it becomes reporting to a manager who then assigns work, it loses both its purpose and its brevity. The servant leader's part is to carry the impediments away and clear them, which is exactly what the current format defers.

    Source: PMP Examination Content Outline (2026), Process domain Task 9 and People domain — daily stand-up purpose; servant leadership and impediment removalReport a problem with this question

  33. 33. Iteration reviews have filled up with long debates about the team's internal process problems, and the stakeholders have started skipping them. What should the project manager do FIRST?

    • A.Merge both purposes into one longer session so stakeholders hear the team's process constraints.
    • B.Drop the review and rely on the retrospective, since the increment has already been demonstrated.
    • C.Keep the review for feedback on the increment and move process issues to the retrospective.Answer
    • D.Invite the stakeholders to the retrospective as well so improvements gain their sponsorship.

    The review inspects the product with stakeholders and adapts the backlog from their feedback, while the retrospective inspects how the team works and produces improvement actions. Keeping the two events distinct protects both: stakeholders retain a reason to attend, and the team retains a candid space that outside attendance would inhibit.

    Source: PMP Examination Content Outline (2026), Process domain Task 3 and Task 9 — iteration review for stakeholder feedback; retrospective for process improvementReport a problem with this question

  34. 34. Midway through the project the team hits an integration problem that an earlier phase had already solved, but nothing was written down because the organization captures lessons at closure. What should the project manager do FIRST?

    • A.Add the item to the closure agenda so it is captured together with the other final lessons.
    • B.Ask the members of the earlier phase to write up what they did so the record becomes complete.
    • C.Record the lesson in the register now and make capture part of the team's regular routine.Answer
    • D.Put the technical fix in the team's wiki so that engineers can find it without extra process.

    The lessons learned register is created early and updated throughout the project precisely so that knowledge reaches the project that is still running; holding lessons until closure delivers them only to future projects. Recording this one now and building the habit addresses both the immediate loss and the practice that caused it.

    Source: PMP Examination Content Outline (2026), People domain Task 7 — help ensure knowledge transfer; lessons learned register maintained throughoutReport a problem with this question

  35. 35. The only engineer who understands a legacy billing interface leaves in three weeks, and she has already written thorough design documents for it. What should the project manager do FIRST?

    • A.Pair another engineer with her on real interface work for the weeks that she has left.Answer
    • B.Have her extend the design documents with troubleshooting steps before she departs.
    • C.Record video walkthroughs of the interface for the team to watch after she has gone.
    • D.Arrange a vendor support contract that covers the interface once she has left the team.

    What is at risk is tacit knowledge — the judgment, shortcuts and failure patterns built from experience — and that transfers through joint work, mentoring and shadowing rather than through artifacts. The explicit part is already documented, so more writing or recording captures only what has been captured already, and a support contract buys cover without transferring anything.

    Source: PMP Examination Content Outline (2026), People domain Task 7 — tacit versus explicit knowledge; pairing, mentoring and shadowingReport a problem with this question

  36. 36. A merger removes the need for a project and the sponsor cancels it, and the team wants to move straight onto its new assignments. What should the project manager do FIRST?

    • A.Archive only the completed deliverables, since a cancelled project reports no benefits at all.
    • B.Release the team at once and write the closure documents after the members are reassigned.
    • C.Run the closing activities, capturing lessons and archiving records, and then release the team.Answer
    • D.Obtain the written cancellation from the sponsor and treat the project as closed on that basis.

    A terminated project is closed in the same way as a completed one: acceptance status is documented, procurements and finances are closed out, lessons and records are archived to the organizational process assets, and only then are resources released. The knowledge a cancelled project produced is often its most valuable output, and it disperses with the team.

    Source: PMP Examination Content Outline (2026), Process domain Task 10 — manage project closure, including closure of a terminated projectReport a problem with this question

  37. 37. A supplier's deliverables have been formally accepted, but the supplier still has an unsettled claim for additional work, and the project manager is preparing administrative closure. What should the project manager do FIRST?

    • A.Settle the claim through the procedure set out in the agreement before closing the contract.Answer
    • B.Close the contract now and pass the claim to the legal department as a separate matter.
    • C.Reject the claim, because the deliverables were accepted without an approved change request.
    • D.Pay the claim from the remaining contingency reserve so that closure is not delayed further.

    Procurement closure requires every claim to be settled, by the dispute-resolution route the contract itself specifies, before the contract is closed out and administrative closure proceeds. Closing around an open claim, paying it outside the contract's process or rejecting it unilaterally each leave a live contractual liability attached to a project that is being declared finished.

    Source: PMP Examination Content Outline (2026), Process domain Task 5 and Task 10 — settle claims and close procurements before administrative closureReport a problem with this question

  38. 38. A manager asks the project manager to publish every team's velocity and to set a target of ten percent growth each iteration. Velocity has been rising, and so have the defects found after release. What should the project manager do FIRST?

    • A.Normalize story points across the teams so that comparisons of velocity become meaningful.
    • B.Explain that velocity forecasts one team's capacity, and propose value and quality measures.Answer
    • C.Publish velocity as asked and add the defect count so that the two figures are read together.
    • D.Set the ten percent target and let each team decide how it will reach that number itself.

    Velocity is a team-specific planning input, not a productivity score, and the moment it becomes a target teams inflate their estimates and trade away quality — which is what the rising post-release defect count already shows. Measures that resist gaming track outcomes the customer feels, such as delivered value, escaped defects and cycle time, rather than internal units.

    Source: PMP Examination Content Outline (2026), Process domain Task 9 — measure and analyze metrics; velocity as a team planning measureReport a problem with this question

  39. 39. Halfway through delivery a cumulative flow diagram shows the in-test band widening steadily while throughput stays flat, yet every milestone is still being reported as on time. What should the project manager do FIRST?

    • A.Examine the growing test queue with the team, since it moves before any of the dates do.Answer
    • B.Add testers to the team so the widening band closes before the next milestone falls due.
    • C.Report the milestones as on track and revisit the diagram if one of them actually slips.
    • D.Recalculate the schedule performance index to confirm whether a real variance exists yet.

    A steadily widening band on a cumulative flow diagram is a leading indicator: work is entering testing faster than it leaves, so delay is accumulating before any date has moved. Milestone status and schedule indices are lagging measures that confirm the problem only after it has cost time, and adding testers commits a remedy before the cause has been established.

    Source: PMP Examination Content Outline (2026), Process domain Task 9 — leading versus lagging indicators; cumulative flow and throughput analysisReport a problem with this question

  40. 40. A system has passed acceptance testing and the sponsor is ready to sign, but the operations staff have not been trained and no support model exists for it yet. What should the project manager do FIRST?

    • A.Assess transition readiness with operations and agree the training and support arrangements.Answer
    • B.Extend the project to run the support itself until operations has capacity to take the system.
    • C.Hand the document set over and ask operations to build its own support model from it.
    • D.Obtain the sponsor's acceptance signature now and schedule the training for the month after.

    Closing a phase or a project includes validating that the receiving organization can actually operate what it is given — training, documentation, support arrangements and operational readiness — and not merely that the deliverable passed its tests. Signing acceptance ahead of that leaves the benefits the project was funded to deliver depending on a handover nobody has planned.

    Source: PMP Examination Content Outline (2026), Process domain Task 10 — validate readiness for transition to operations or the next phaseReport a problem with this question

  41. 41. Two-thirds of the budget has been spent when a competitor's launch removes the market for the product. The sponsor wants to continue because so much has already been invested. What should the project manager do FIRST?

    • A.Continue to completion, because the money already committed would otherwise be wasted.
    • B.Recommend cancelling at once, since the benefits the project was funded for no longer exist.
    • C.Cut the scope to a minimal release so the project finishes inside the budget that remains.
    • D.Reassess the business case on remaining cost against remaining benefit and present the result.Answer

    Money already spent is sunk and irrelevant to the decision; what matters is whether the cost still to be incurred is justified by the benefit still achievable. The project manager rebuilds that comparison and puts it in front of the governance body that owns the continue-or-terminate decision, so recommending cancellation before the analysis exists is the same error pointing the other way.

    Source: PMP Examination Content Outline (2026), Process domain Task 3 — examine business value throughout the project; sunk cost excluded from go/no-go decisionsReport a problem with this question

Practice questions based on the PMI PMP Examination Content Outline and standard project-management frameworks (PMBOK Guide, Agile Practice Guide). PMP and PMBOK are marks of the Project Management Institute; this site is not affiliated with or endorsed by PMI. Study the official Exam Content Outline and confirm current requirements before testing. About the PMP exam →