Chapter 4 · Lesson 2 of 4
Business impact analysis, RPO, RTO and alternate sites
1 min read
Continuity planning starts with a business impact analysis (BIA). It identifies mission-critical functions, ranks how critical each one is, and weighs the impact of losing it. The recovery targets come out of the BIA; they are never a number handed in by the IT team beforehand.
- Recovery point objective (RPO): the most data loss the business can tolerate, measured in time back from the failure. Backup or replication frequency sets it.
- Recovery time objective (RTO): how long restoring the system may take, measured forward from the failure.
- Maximum tolerable downtime (MTD): the outer business limit on the outage. Restoration plus the work recovery time needed to clear the backlog must fit inside it.
Example: an MTD of 8 hours, a 5-hour restore and 2 hours to clear the backlog gives 5 + 2 = 7 hours, so the plan fits. If the restore took 7 hours, 7 + 2 = 9 hours would exceed the limit.
Alternate sites trade cost against speed: a cold site has only space and power and takes weeks, a warm site has hardware but needs data loaded, and a hot site is live within minutes or hours. A reciprocal agreement with another company is cheapest, but its spare capacity is unverified and each side may see the other's data.
Check yourself
1. A continuity team records a maximum tolerable downtime of eight hours for a claims system. Technology can restore the platform in six hours, after which claims staff need three more hours to clear the backlog before the function is genuinely running again. What should the team conclude?
2. A firm's business impact analysis sets a four-hour recovery target for its trading platform, while finance prefers the cheapest alternate site on offer. Which choice should the continuity manager defend?
Facts checked 2026-11-15 · Sources: ISC2 Certified in Cybersecurity (CC) Exam Outline, NIST SP 800-34 Rev. 1: Contingency Planning Guide for Federal Information Systems, CISA #StopRansomware Guide